Monday, November 4, 2013

Excavation & footings

Excavation started on October 30th.  On October the 31th, connections were made for power, sewer, and water.  Footing materials were delivered along with a 1000 lb plate tamper.  Geotechnical and plumbing & electrical inspections were done near noon on the 31st.  The 24" x 8" footings with 3 rows of 15 mm rebar were placed on the afternoon of the 31st and the morning of November 1st.  Footing were inspected at 2:30 PM on Friday, concrete was poured at 3:30 PM.

No comments:

Post a Comment